Few Michigan development issues sit as directly at the intersection of the 2026 election, electricity prices, local land use and state tax policy as hyperscale data centers.
Gov.-elect Jocelyn Benson campaigned on a moratorium on new data-center projects until Michigan adopts guardrails covering public hearings, transparency, water use, electricity costs and tax incentives. That policy position now moves from campaign proposal to an issue for the incoming administration and Legislature.
Two large projects are already far beyond the idea stage
In Van Buren Township, the Michigan Public Service Commission approved special DTE Electric contracts for a Google data center on October 1, 2026. The agreement includes requirements intended to prevent other DTE customers from paying project costs and calls for Google-funded new renewable generation and storage.
In Saline Township, the MPSC had already conditionally approved electric-service contracts for a roughly 1.4-gigawatt data center associated with Green Chile Ventures, Oracle, OpenAI and Related Digital. The Attorney General has challenged aspects of that approval.
Those cases are important because a campaign promise for a moratorium does not automatically answer whether projects with prior utility, local or state approvals would be covered. That will depend on the legal form and timing of any new policy.
What Benson proposed during the campaign
Benson’s campaign called for pausing new data centers until enforceable rules require public hearings and disclosure, prevent developers from shifting electricity costs to other customers, protect natural resources and end state tax breaks for data centers.
Michigan currently offers sales-and-use-tax exemptions to qualifying data-center projects under state law. Changing those statutory exemptions would generally require legislation, not simply an executive announcement.
Why the election matters for local communities
The incoming governor will influence agency appointments, regulatory priorities and the state budget. The incoming Legislature can amend tax statutes and create new siting or disclosure rules. Local governments still retain important zoning and land-use roles, while the MPSC governs utility-service questions within its jurisdiction.
That means future projects could face a materially different approval environment even if already-advanced Van Buren and Saline developments continue through existing processes.
What to track in 2027
- Whether a formal moratorium is proposed and what projects it covers.
- Whether the Legislature changes the Enterprise Data Center sales-and-use-tax exemption.
- Whether new public-hearing or resource-disclosure rules are enacted.
- How the MPSC handles large-load contracts and ratepayer protections.
- The outcome of pending legal challenges involving existing projects.
Michigan Progress will treat each data-center project as a development record with separate milestones for local approvals, utility contracts, state incentives and construction. See the broader Michigan Development Tracker and township database for local context.