Michigan Data Centers After the 2026 Election: Van Buren, Saline and New Projects Face a Policy Reset

Gov.-elect Jocelyn Benson campaigned for a moratorium on new data centers until new guardrails are in place, while major Van Buren and Saline projects already have utility approvals.

Michigan Progress analysis · data vintages and primary sources identified in the article

Few Michigan development issues sit as directly at the intersection of the 2026 election, electricity prices, local land use and state tax policy as hyperscale data centers.

Gov.-elect Jocelyn Benson campaigned on a moratorium on new data-center projects until Michigan adopts guardrails covering public hearings, transparency, water use, electricity costs and tax incentives. That policy position now moves from campaign proposal to an issue for the incoming administration and Legislature.

Two large projects are already far beyond the idea stage

In Van Buren Township, the Michigan Public Service Commission approved special DTE Electric contracts for a Google data center on October 1, 2026. The agreement includes requirements intended to prevent other DTE customers from paying project costs and calls for Google-funded new renewable generation and storage.

In Saline Township, the MPSC had already conditionally approved electric-service contracts for a roughly 1.4-gigawatt data center associated with Green Chile Ventures, Oracle, OpenAI and Related Digital. The Attorney General has challenged aspects of that approval.

Those cases are important because a campaign promise for a moratorium does not automatically answer whether projects with prior utility, local or state approvals would be covered. That will depend on the legal form and timing of any new policy.

What Benson proposed during the campaign

Benson’s campaign called for pausing new data centers until enforceable rules require public hearings and disclosure, prevent developers from shifting electricity costs to other customers, protect natural resources and end state tax breaks for data centers.

Michigan currently offers sales-and-use-tax exemptions to qualifying data-center projects under state law. Changing those statutory exemptions would generally require legislation, not simply an executive announcement.

Why the election matters for local communities

The incoming governor will influence agency appointments, regulatory priorities and the state budget. The incoming Legislature can amend tax statutes and create new siting or disclosure rules. Local governments still retain important zoning and land-use roles, while the MPSC governs utility-service questions within its jurisdiction.

That means future projects could face a materially different approval environment even if already-advanced Van Buren and Saline developments continue through existing processes.

What to track in 2027

  • Whether a formal moratorium is proposed and what projects it covers.
  • Whether the Legislature changes the Enterprise Data Center sales-and-use-tax exemption.
  • Whether new public-hearing or resource-disclosure rules are enacted.
  • How the MPSC handles large-load contracts and ratepayer protections.
  • The outcome of pending legal challenges involving existing projects.

Michigan Progress will treat each data-center project as a development record with separate milestones for local approvals, utility contracts, state incentives and construction. See the broader Michigan Development Tracker and township database for local context.

Sources

FAQ / AEO

Questions about this analysis

Direct answers based on the evidence and methodology used on this page.

Did Michigan ban data centers in the 2026 election?

No. There was no statewide data-center ballot ban. Gov.-elect Jocelyn Benson campaigned on a moratorium for new projects until new guardrails are adopted.

Is the Google data center in Van Buren Township already approved?

The Michigan Public Service Commission conditionally approved DTE Electric service contracts for the Google data center on October 1, 2026. The MPSC decision concerns utility service, not every local, environmental or land-use approval.

What about the Saline Township data center?

The MPSC conditionally approved DTE service contracts for the approximately 1.4-gigawatt Saline Township data center in December 2025. The Attorney General has challenged aspects of the approval process.

Could the new governor change Michiganu2019s data-center tax breaks?

The incoming administration can propose changes, but statutory tax exemptions generally require legislative action. The exact treatment of already-certified projects would depend on enacted law and existing approvals.

Ryan Richmond
ABOUT THE AUTHOR

Ryan Richmond

Ryan Richmond has a background in commercial and residential real estate in Michigan. He writes about property values, development, local economies and the measurable forces shaping Michigan communities. Get in touch with Ryan for your commercial and residential real estate needs in Metro Detroit: ryan@realtyplus.com